War Memorial Stadium/Jonah Field Preparation - Photo Gallery

July 5, 2005

LARAMIE, Wyo. -

The project remains on schedule. The new goal posts have been installed and painted. The contractor is completing installation of the underground drain piping, and is spreading a crushed rock field base. Two new entrances to the stadium have been poured on the east side. South endzone bleachers are being removed and the new turf has started to be delivered in rolls.

A drainage trench under the field before the pipe and tarp is laid.

Partially installed new goalposts in the north endzone.

New goalposts are installed in the south endzone.

Tarps are laid, then topped with crushed rock.

Drainage pipes before they are covered with crushed rock.

The north goalposts are painted.