War Memorial Stadium Field Preparation - Photo Gallery

June 21, 2005

LARAMIE, Wyo. -

The project is on schedule. Foundations for the goal posts have been poured. The contractor is pouring the concrete aprons on each side of the field for the trench drains and starting to install the underground drain piping. Two new entrances to the stadium are being prepared on the east side, as well as a new entry ramp into the student section from the southeast corner.

Old concrete was removed along the sidelines and endzones.

Concrete aprons are poured on each side of the field for the trench drains.

Concrete aprons are poured on each side of the field for the trench drains.

The facade on the east side has been painted gold and Wyoming's bowl teams will be relettered.

Underground drain piping is installed in the south endzone.

Underground drain piping is installed in the south endzone.